St. Petersburg City Council takes up a new Dalí Museum lease Dec. 3 that moves the planned expansion south of the museum. A public hearing is set for Dec. 10.
Overview
The Dalí Museum’s planned expansion has moved. The museum now plans to build most of it to the south of the existing building, in what is now its loading dock area, according to a city staff memo. It has dropped the “elevated concept” to the west that voters and the City Council cleared the way for earlier.
St. Petersburg City Council will hear a rewritten lease for the museum’s city-owned waterfront land at its meeting Thursday, Dec. 3. That is the first reading. The public hearing and final vote are set for Thursday, Dec. 10.
What the new lease changes
The museum sits on city land under a 99-year lease signed Nov. 29, 2007. The new document, Ordinance 664-H, is a “Second Amended and Restated Lease.” It is in the Dec. 3 agenda packet as item E-4.
The staff memo lists the main changes from the version the council approved in December 2024:
- the conceptual plat and lot diagram are redrawn for the new design
- references to the “elevated concept” are removed, and the terms are broadened to allow the new design and future changes
- the Phase 2 milestones for design and construction are updated
- the review process for the museum’s plans is updated
- fire safety and other statutory references are brought up to date
- the remaining terms of a 2010 grant agreement are folded into the lease, so the old agreement can end
- all existing protections for the Grand Prix race are kept
The ordinance would also let the city swap in updated plat and lot drawings later without a new vote. The condition is that they stay “substantially similar” to the ones the council sees now.
The memo says the museum asked to sign the amendment before the end of 2026. To meet that, the city is sending it to the council before museum leadership has fully approved it. Administration said it believes the version on the agenda “meets the needs of both parties.” There is no cost to the city, the memo says.
How the plan got here
The expansion has been through several versions, the memo says:
- 2019: Pinellas County and its tourist development commission committed money for a parking garage on the museum’s surface lot. The city found the garage could not be built while meeting its contracts with the Mahaffey Theater and the Firestone Grand Prix of St. Petersburg.
- 2021: The museum proposed a building to the west instead, on a strip of city right-of-way known as Lot 6. A citywide referendum was drafted, then dropped when the museum withdrew the request.
- Nov. 8, 2022: Voters approved a referendum under Ordinance 512-H that set out how the lease could be changed to use Lot 6.
- December 2024: The council approved a lease amendment for the elevated design.
- 2026: The design shifted south, to the loading dock area, which needs the rewritten lease now on the agenda.
The museum’s plan
The museum announced the expansion design in March. Its release describes an addition of about 35,000 square feet. The museum put the cost at an estimated $70 million, with early support from Visit St. Pete-Clearwater’s tourist development tax funds.
The museum said The Beck Group, which built the 2011 building, will design and build the addition. It said the new space will hold galleries for exhibitions that mix art and technology, a learning center for K-12 students and adults, and event space.
In March, the museum said groundbreaking was expected in fall 2026 and that the expanded spaces should open in 2028. It said it will stay open during construction. The museum has not published a new date since the design moved.
The timeline in the lease
The new lease sets deadlines the museum must meet, in six stages. The first, a concept plan, is listed as complete. After that:
| Stage | Deadline in the lease |
|---|---|
| Preliminary design (60% of design work) | 90 days after the new lease is signed |
| Preparation for site and foundation work | 265 days after city comments on the preliminary design |
| Construction documents and permits | 180 days after city comments on the site stage |
| Substantial completion of construction | 720 days after the permit stage begins |
The lease treats those deadlines as firm. Before work starts, the museum must show the city a signed construction contract, proof of funding and a performance and payment bond. The lease also asks for an airport regulation analysis and copies of approved permits, including from the FAA.
The museum’s surface parking lot must be free for race use from three days before the Grand Prix set-up period until the race is dismantled, the lease says.
Also on the Dec. 3 agenda
The council meets at 1:30 p.m. Public hearings start at 5:01 p.m. Other items on the agenda include:
- a public hearing on Ordinance 655-H, which would raise the density and height limits in three zoning districts outside the Coastal High Hazard Area
- a public hearing on Ordinance 659-H, on loud noise from vehicles on city streets
- a $1,445,108 contract with Ajax Building Company for the Mahaffey Theater roof
- declaring the 41st Annual St. Pete MLK Parade on Jan. 18, 2027, a special event
- a Community Redevelopment Agency review of two 44-story towers with 325 homes and 17,988 square feet of commercial space at 333 1st Street South
What it means for you
- The Dalí stays open. The museum said it will not close during construction.
- Thursday’s vote is only the first reading. Public comment on the lease is taken at the Dec. 10 hearing, in person at the council meeting.
- You can watch both meetings live at stpete.org/TV or on Channel 15 WOW!, Channel 641 Spectrum and Channel 20 Frontier FiOS.
- The museum posts its renderings and timeline on its expansion site.